State-owned NBCC i.e. National Building Construction Corporation said that they will submit a detailed project report (DPR) of Amrapali Group’s 16 stalled projects to the Supreme Court in the coming week and are thinking about developing similar projects of other real estate firms.

The Supreme Court, in September, appointed NBCC to develop stalled projects of the Amrapali Group following the company’s proposal that it could complete all the stuck projects, comprising 46,575 flats, within 36 months at a construction cost of Rs 8,500 crore.

NBCC’s CMD Anoop Kumar Mittal gave an update on the Amrapali matter and said that the company has issued tenders for 10-11 out of the 16 stalled projects. He further said “In next one week, we will issue tenders for 5-6 projects. The DPR for all 16 projects will be submitted to the apex court in one week’s time.”

CMD Mittal also added that the work on Amrapali projects would start after approval from the Supreme Court. Asked about funding, he said this would be decided by the apex court.

Mittal also announced that NBCC would soon come up with a policy for development of new and stalled real estate projects in larger public interest. He also said that “We can act as project management consultant or co-developer or developer for real estate projects and that project could come up in joint venture.

Mittal said NBCC in the next two months would be in a position to start construction works at Netaji Nagar and Sarojini Nagar redevelopment projects after High Court gave clearance to its revised plan. The company would take fresh approvals from the local bodies, if needed.

CMD also said that “We have started redesigning the project as per our revised plan submitted to the court.”

Mittal said the company has bagged two projects in the national capital from Air India and expects to start work in the next 3-4 months. On railway station redevelopment, he said the company has started work on two stations and would soon begin work on two other stations. The tenders for six other stations would also be floated soon. He also said that “By March, construction works in all 10 rail projects will start. We hope to complete these projects on time.”

Shilpa Sardare Jain
Shilpa Sardare Jain is a journalist and works as a content writer with us. Her journalistic background helps her cater the viewers with accurate news about everything around. She is experienced at writing articles, blogs, features and news related to different genres. She started her career with News24 News channel and then worked with a leading digital media channel One India News and few others. Shilpa Sardare Jain is a joyful person who loves to explore new places and food when not working. Also, she has the zest for reading autobiographies of politicians who took the world by storm.